Milton Village Redevelopment


Exciting changes are underway at Milton Village, and we want to assure you that we’re open for business throughout the redevelopment process. Here’s a glimpse into what’s happening and how it might affect your visit:

 

Redevelopment Timeline:

  • Stage 1 (August 2023 – March 2024): New toilets & temporary works, relocation of power to medical & infrastructure, shop demolition. 
 
  • Stage 2 (March 2024 – June 2024): Demolition of IGA at the end of the centre. 
 
  • Stage 2A (March 2024 – November 2024): Closure of basement carpark. 
 
  • Stage 2B (May 2024 – Mid 2025): Construction of the new Coles Local and new upper level.
 

Temporary Changes Due to Redevelopment Works:

  • Car Park Access: The front car park will revert to two-way access from a widened southern entrance to maintain parking bays.
 
  • Drop Zone: Angled parking bays in front of the Izakaya Kura Restaurant will be converted into a drop zone during busy times.
 
  • Loading: Rear loading for tenancies will no longer be possible. Deliveries will occur at designated road load zones or through the front of shops. Please contact individual retailer to arrange best delivery. 
 

We understand that change can bring challenges, but we’re committed to minimising disruptions and ensuring a seamless experience for our valued customers. Thank you for your patience and continued support as we embark on this exciting journey of transformation. Stay tuned for updates, and remember, Milton Village is open and thriving throughout the redevelopment.


Thank you, 

Centre Management